New Build EPCs and Site Visit Requirements for NDEAs
Charlotte Lancaster
Last Update 7 days ago

Non-domestic EPC assessments are not always carried out on existing, occupied buildings.
An assessor may also be instructed to produce an EPC for:
- a newly constructed commercial building;
- a shell-and-core building;
- a newly completed extension;
- a building that has undergone a major change;
- or a building where a previously unconditioned space has become conditioned.
These situations require a slightly different approach from a standard existing-building assessment.
For an existing building, the assessor will normally visit the property, inspect its fabric and services, take photographs, record measurements and build the assessment from what is physically present.
For a genuine new-build assessment, much of the evidence can instead come from the design team, developer and Building Control documentation.
Understanding the distinction is important because it determines:
- whether a site visit is required;
- what evidence can be relied upon;
- how the building should be classified;
- and which Building Regulations requirements apply.
What is a new-build non-domestic EPC?
For example:
A new two-storey office block is constructed on a previously vacant site.
This is clearly a newly constructed building.
Once construction is physically complete, the person responsible for the construction must provide the building owner with an EPC and recommendation report and notify Building Control that this has been done. Building Control will not issue its completion certificate until it is satisfied that this requirement has been met.
However, an NDEA may encounter less obvious situations which are treated in a similar way.
Examples may include:
- first fit-out of a shell-and-core unit;
- a substantial extension;
- a building becoming conditioned for the first time;
- or certain relocated modular buildings.

New-build assessments are Level 4
This means that an assessor completing the assessment must hold the appropriate Level 4 qualification and accreditation.
Level 3 assessors may assess many straightforward existing commercial buildings, but new-build work falls outside the Level 3 scope.
This is important for learners because the software used may look familiar, but the complexity classification and evidence requirements are different.
Existing building versus new-build assessment
That requirement is specifically concerned with existing-building assessments.
The approach to genuine new-build assessments is different because the assessor is certifying the completed building using the documentation supplied for the construction.
When may a site visit not be required?
Examples include a building that:
Has been constructed completely from newFor example:
A new office is constructed from foundations upwards on a previously vacant site.The assessor can work from the completed design and as-built documentation.
Is undergoing its first shell-and-core fit-out
A shell-and-core building may be completed before the final occupier's services and internal fit-out are installed.
The Government guidance recognises shell-and-core buildings and explains that where the building is expected to be conditioned but services have not yet been installed, an EPC must still account for the expected fixed services.
The important concept is first fit-out.
A shell-and-core condition does not continue indefinitely.Once a unit has been fully fitted out and occupied, it cannot later be stripped back and treated as a brand-new shell-and-core building simply because the services have been removed.
Has undergone a change of energy status
The Building Regulations define a change to a building's energy status as a change that causes the building to become subject to the energy-efficiency requirements where it was not previously subject to them.
For example:
An unheated agricultural or storage building is converted into a heated office complex.The previously unconditioned building has now become a conditioned building.
Regulation 22 requires work to be carried out where necessary so that the building complies with the applicable requirements of Part L.
Care is required here.A change of energy status is not the same thing as simply adding heating to one room within an otherwise conditioned building.

Extensions and the 100 m² / 25% rule
A commonly encountered rule is:
The extension must be greater than 100 m² AND greater than 25% of the total useful floor area of the existing building.Both conditions must be satisfied.
This threshold is used within Building Regulations guidance to determine when a large extension should follow the new-building approach to Part L.

When would a site visit normally be required?
A site visit would normally be expected where the assessor is assessing an existing conditioned building.
Existing building stripped out and refurbished
- Consider an office that has existed for many years.
- The occupier moves out and the building is stripped back internally. New lighting, HVAC and finishes are installed.
- The building has not suddenly become a new building.
- It remains an existing building that has undergone refurbishment.
- A survey is therefore required to establish what actually exists.
- The Government guidance gives a similar example of a building undergoing a complete internal refit. A refit alone does not necessarily trigger the requirement for a new EPC.
Part of an existing building becomes conditioned
- Suppose a warehouse already contains heated offices.
- The warehouse storage area has previously been unheated but heating is now installed.
- This is not the same as constructing an entirely new building.
- The assessor must establish the existing building and the altered section correctly.
Smaller extension
- Where an extension does not meet both of the large-extension thresholds discussed earlier, it does not automatically follow the new-building approach applicable to large extensions.
- If an EPC is required for the whole existing building, the assessor must appropriately assess the existing building as well as the extension.

Do not confuse an EPC trigger with Building Regulations work
- replacement heating;
- new lighting;
- air-conditioning replacement;
- an internal refurbishment;
- or insulation upgrades.
The work may need to comply with Building Regulations.
However, that does not necessarily create an EPC trigger.
Building Regulations compliance and the requirement to produce an EPC are related, but they are not the same question.An assessor should establish why the EPC is being produced before deciding how to approach the assessment.
The assessor's role on a new-build EPC

- construction specifications;
- U-value calculations;
- glazing specifications;
- HVAC schedules;
- lighting schedules;
- air-pressure test certificates;
- commissioning information;
- BRUKL documents;
- drawings;
- and Building Control documentation.
The assessor uses these documents to build and support the EPC model. The assessor should not redesign the building or substitute their judgement for Building Control.
Proposed drawings are not automatically as-built evidence
Proposedor
Construction Issuedoes not automatically prove that the building was actually constructed exactly that way.
- insulation products may change;
- boilers may be substituted;
- lighting layouts may be altered;
- window specifications may change;
- HVAC equipment may be replaced with an equivalent model;
- room layouts may move;
- or control systems may change.
The assessor therefore needs confirmation of the as-built condition.

Evidence requirements changed on 1 October 2026
The requirements apply to both existing and newly constructed non-domestic buildings, although the evidence expected is not identical in each case.
- the assessment data file;
- floor plans;
- elevations and sections;
- zone drawings and schedules;
- construction specifications;
- building-services information;
- product literature;
- calculations;
- airtightness information;
- as-built confirmation;
- and evidence supporting recommendations.
The underlying principle is simple:
An auditor should be able to understand and reproduce the assessment from the evidence retained.The new requirements do not change the calculation methodology themselves. They formalise the baseline level of evidence that assessors must retain.
References and further reading
Covers EPC triggers, new construction, modifications, shell-and-core buildings and the responsibilities of the assessor and building owner.
Refer particularly to Regulation 22 regarding a change to a building's energy status.
Effective from 1 October 2026 for England and Wales.
https://easob.co.uk/NDEA_Minimum_Evidence_Requirements.pdf
The conventions should be used alongside the applicable NCM methodology and accreditation-scheme guidance when determining assessment inputs and handling missing services.